The membrane gas holder works for the 500 m³ Biogas Storage and Peak Regulation Project at a Shanghai Distillery, undertaken by Qingdao Haiyue have recently been completed. Following installation and commissioning, the system has officially entered operation.
Capacity: One 500 m³ double membrane gas holder
Application: Collection of biogas from anaerobic treatment, constant-pressure storage and peak regulation, supporting downstream boiler operation or power generation
Scope: Membrane structure design, membrane fabrication, foundation construction, membrane erection and tensioning, pressure regulation system, safety interlocks, and integrated commissioning
Supplier: Qingdao Haiyue
![]()
Foundation acceptance and bottom membrane installation
Inner and outer membrane erection and tensioning, successfully completed on the first attempt
Airtightness and pressure tests, passed on the first attempt
Integrated commissioning of the blowers, control cabinet, and flare system
Final handover